2021 Dec 31st
Sainshand Salkhin Park LLC
LTI free 1199 days
193'278'294 kW of pwer supplied to the Central Power System as of December 31, 2021.
2020 Dec 31st
Sainshand Salkhin Park LLC
LTI free 834 days
160'651'524 kW of power was supplied to the Central Power System as of December 31, 2020.
2019 Jan
Sainshand Salkhin Park LLC
Started generating electricity
Power supply to the Central Power System started on January 17, 2019.
2019 Jan 19th
Sainshand Salkhin Park LLC
COD
2018 Dec 18th
Sainshand Salkhin Park LLC
State commission has been completed.
2018 Nov 18th
Sainshand Salkhin Park LLC
Dry close.
2018 May 18th
Sainshand Salkhin Park LLC
First wind turbine is connected.
2017 Nov 17th
Sainshand Salkhin Park LLC
Complation of first 4 foundations.
2017 Oct 17th
Sainshand Salkhin Park LLC
Construction started
2017 Aug 17th
Sainshand Salkhin Park LLC
Financial Close reached
2016
Sainshand Salkhin Park LLC
Amended and bankable PPA signed with NDC
Final discussions with lenders.
2015
Sainshand Salkhin Park LLC
Renewed bankable environmental assessment
2013
Sainshand Salkhin Park LLC
Installation of bankable wind met mast.
2011
Sainshand Salkhin Park LLC
Special permission to build granted by Energy Regulatory Commission
PPA signed with NDC.
2009
Sainshand Salkhin Park LLC
Asset initiated by Mr.Davaanyam
Construction approved by Ministry of Environment.